The table below represents the recommended business practices for tag submission and assessment deadlines for Interchange Transactions whose Sink Control Areas are within the Eastern Interconnection. The table describes the various recommended minimum submission and assessment timing requirements. To the extent an entity utilizes a different practice than the one recommended in this Policy the entity shall:

·         File and have the practice accepted by its regulator.

·         Submit an explanation to NERC of the differences in its regulator-approved practice and Policy 3.
  

Transaction Duration

PSE Submit Deadline

Actual Tag Submission Time

Provider Assessment Time

Time to Start of Transaction (Not Start of Ramp)

Less than 24 Hours

20 Minutes prior to start

< 1 Hour prior to start

£ 10 Minutes from tag receipt

³ 10 Min

> 1 to <4 hours prior to start

£ 20 Minutes from tag receipt

³ 40 Min

³ 4 Hours prior to start

£ 2 Hours from tag receipt

³ 2 Hours

24 Hours or longer

4 Hours prior to start

Any

£ 2 Hours from tag receipt

³ 2 Hours

 Below is a listing of the Standard submission times,   other entities non-standard submission times, and Comments on submission times.  Non-Standard items and comments will be listed in red.

Actual Tag Submission Time
     <= 1 Hour prior to start
     >= 1 to <= 4 Hours prior to start
     >= 4 Hours prior to start
     Any
     < noon of the Day Ahead
     >= noon of the Day Ahead
Comment
     Read our tariff if you want to know about our practices! Go to www.nerc.com
Provider Assessment Time
     <= 2 Hours from tag receipt
     <= 10 Minutes from tag receipt
     <= 20 Minutes from tag receipt
PSE Submit Deadline
     4 Hours prior to start
     20 Minutes prior to start
     s
     5 minutes
     Regardless of duration, if it is for Day-Ahead, then the deadline is prior to the noon Energy Market Daily Trading Deadline, unless using PJM Non-Firm Hourly Transmission Service that is released by PJM at noon, in which case up to 30 minutes after noon.
     Regardless of duration,if it is for Short Notice, i.e., after the noon Energy Market Daily Trading Deadline, then the PSE Submit Deadline is 90 minutes prior to start.
Time to Start of Transaction (Not Start of Ramp)
     >= 40 Minutes
     >= 2 Hours
     >= 10 Minutes
Transaction Duration
     Less than 24 Hours